Winnipeg bridge construction project cost increasing

Share

The price tag for the St. Vital Bridge project is going up.

A report to the Public Works committee is requesting a $6 million contract over expenditure.

That would push the total cost to nearly $49 million.

Two million dollars is needed because the bridge’s pier on the north riverbank has recently moved.

The report says urgent work is required as a soon as the water level on the Red River recedes.

“The results have indicated that with the recent movements, the bridge pier foundation capacity will be exceeded under combinations of permanent and in-service loads.” The report states. “Work is required to ensure the long-term stability of the bridge.”

The report says the other riverbank piers are also being checked as a precautionary measure.

Four million dollars is also needed for steel girder preservation coating, which the report says will add a minimum “50-year life service” to the bridge.

The report says the extra $6 million still falls within the projected budget amounts.

Work on the bridge will continue until August 2025. However, it will not affect the opening of the bridge to full traffic, which is expected in November 2024.

CTVNews.ca Top Stories

BREAKING

BREAKING Honda to get up to $5B in govt help for EV battery, assembly plants

Honda is set to build an electric vehicle battery plant next to its Alliston, Ont., assembly plant, which it is retooling to produce fully electric vehicles, all part of a $15-billion project that is expected to include up to $5 billion in public money.

Secret $70M Lotto Max winners break their silence

During a special winner celebration near their hometown, Doug and Enid shared the story of how they discovered they were holding a Lotto Max ticket worth $70 million and how they kept this huge secret for so long.

Stay Connected