Winnipeg bridge construction project cost increasing

The price tag for the St. Vital Bridge project is going up.

A report to the Public Works committee is requesting a $6 million contract over expenditure.

That would push the total cost to nearly $49 million.

Two million dollars is needed because the bridge’s pier on the north riverbank has recently moved.

The report says urgent work is required as a soon as the water level on the Red River recedes.

“The results have indicated that with the recent movements, the bridge pier foundation capacity will be exceeded under combinations of permanent and in-service loads.” The report states. “Work is required to ensure the long-term stability of the bridge.”

The report says the other riverbank piers are also being checked as a precautionary measure.

Four million dollars is also needed for steel girder preservation coating, which the report says will add a minimum “50-year life service” to the bridge.

The report says the extra $6 million still falls within the projected budget amounts.

Work on the bridge will continue until August 2025. However, it will not affect the opening of the bridge to full traffic, which is expected in November 2024.

CTVNews.ca Top Stories

BREAKING

BREAKING Murder charge laid in killing of B.C. Mountie

The day after an RCMP officer was killed and two others were injured while executing a search warrant in Coquitlam, B.C., charges of murder and attempted murder have been laid.

Ford offers Unifor wage increases up to 25 per cent

Ford Motor has offered Canadian union Unifor wage increases of up to 25 per cent in its tentative agreement, the union said on Saturday. The agreement provides a 10 per cent wage increase for the first year followed by increases of two per cent and three per cent through the second and third year and a $10,000 productivity and quality bonus to all employees on the active roll of the company, Unifor said.

Stay Connected